|
Application:
Model testing to establish that the proposed pumping station
layout and dimensions were adequate for both summer and winter operation
Site: Al-Shuaiba
Pumping Station, Kuwait
Service:
Physical Modelling
Problem:
For winter operation, a minimum flow rate of 60,000 m³/hr and a
maximum flow of 105,000 m³/hr was needed. Initially nine pumps with
a flow capacity range of between 3.65m3/s to 5.50m3/s (run out)
were proposed, with the option of installing one additional standby
pump in the future. In winter, a maximum of eight pumps and one
or two cooling towers would operate. For summer operation the station
capacity would be a minimum flow rate of 75,000 m³/hr and a maximum
of 105,000 m³/hr. Again a maximum of 8 pumps would operate, with
flow entering through both of the cooling towers.
|
 |
Objectives:
To construct and test a 1:10 hydraulic scale model of the pumping
station to demonstrate that the proposed pumping station layout,
dimensions and operation were suitable for:
a. winter
operation
b. summer operation.
Approach:
A total of ten pumps were installed in the model arrangement and
used in the test matrix. The test programme included the operation
of the station when certain sections were isolated for maintenance
purposes.
Outcome:
Following extensive testing of the scaled hydraulic model, modifications
to the initial design were proposed. These included:
- the installation
of flow splitting vanes beneath each pump intake to suppress the
excessive swirl or pre rotation of the intake flow
- vertical
blades attached to the rear wall of the pump cells to further
stabilise flow conditions at the pump intakes and sections of
tapered benching positioned either side of the pump units to prevent
the formation of submerged vortices
Flow conditions
in the cooling tower outlet sumps at single tower operations were
found to be very aerated at the minimum pump cell water surface
elevations and high station flows. The aeration was seen to moderate
as the water level rose above the minimum or when both towers were
operating.
The model functionally
demonstrated and optimised design, provided a comparison of design
solution options, and facilitated performance observation and assessment
by the project team.
For more information,
or to discuss your case, please contact
us.
|